THERMAL POWER PLANT STANARI AUTUMN OVERHAUL

The Annual Power Generation Plan anticipates two overhauls to the Thermal Power Plan Stanari in 2019. The first, major overhaul was successfully completed in April. Thanks to the dedicated TPP personnel who worked together with the staff from other local and regional companies to perform maintenance and inspection of the boiler-turbine units and BoPs, the TPP Stanari was back to the grid in 30 days.

The TPP Stanari starts the second overhaul with preventive maintenance on Sunday, September 29. During this autumn overhaul the EFT personnel will be assisted by the staff from other local companies to prepare the plant for winter operation conditions. The overhaul activities are anticipated to be completed in approximately 10 days.

With the 1 523 000 MWh generated since the beginning of 2019 up to date, the Thermal Power Plant Stanari keeps fulfilling its Annual Generation Plan.