Construction progress
EPC contract effective date |
21 December 2012 |
Planned completion of TPP construction |
21 September 2016 |

Foundation excavation commencement |
April 2013 |

Steel structure installation commencement |
September 2013 |

Boiler drum positioning |
March 2014 |

Steam turbine erection commencement |
June 2014 |

Chimney wind shield erection completion |
July 2014 |

Boiler hydraulic test completion |
December 2014 |

Connection to the 110 kV transmission grid |
March 2015 |
Commencement of water treatment plant operation |
May 2015 |

Commencement of coal receiving on TPP |
June 2015 |

Taking Over of TPP Stanari from the EPC Contractor |
8 August 2016 |

TPP Stanari Commercial Operation |
20 September 2016 |