Construction

Construction progress

EPC contract effective date

21 December 2012

Planned completion of TPP construction

21 September 2016

Foundation excavation commencement

April 2013

Steel structure installation commencement

September 2013

Boiler drum positioning

March 2014

Steam turbine erection commencement

June 2014

Chimney wind shield erection completion

July 2014

Boiler hydraulic test completion

December 2014

Connection to the 110 kV transmission grid

March 2015

Commencement of water treatment plant operation

May 2015

Commencement of coal receiving on TPP

June 2015

Taking Over of TPP Stanari from the EPC Contractor

8 August 2016

TPP Stanari Commercial Operation

20 September 2016